Project Timeline

2026-2028
Anticipated construction period. Details of deliveries, traffic management measures and construction activities can be found here.
..............................................................................................................
November 2025
Anticipated commencement of development
..............................................................................................................
Spring 2025
Satisfaction and Discharge of Conditions
..............................................................................................................
November 2022
Project approved at appeal by Scottish Ministers
..............................................................................................................
Winter 2019/20
Application submitted for planning permission to Argyll and Bute Council
..............................................................................................................
Autumn 2017 and Spring 2019
Public consultation in the form of two public exhibitions to be undertaken
..............................................................................................................
August 2017
Submission of Scoping Report to Argyll and Bute Council
..............................................................................................................
September 2016
Environmental Impact Assessment started