Project Timeline

2026-2028

Anticipated construction period. Details of deliveries, traffic management measures and construction activities can be found here.

..............................................................................................................

November 2025

Anticipated commencement of development

..............................................................................................................

Spring 2025

Satisfaction and Discharge of Conditions

..............................................................................................................

November 2022

Project approved at appeal by Scottish Ministers

..............................................................................................................

Winter 2019/20

Application submitted for planning permission to Argyll and Bute Council

..............................................................................................................

Autumn 2017 and Spring 2019

Public consultation in the form of two public exhibitions to be undertaken

..............................................................................................................

August 2017

Submission of Scoping Report to Argyll and Bute Council 

..............................................................................................................

September 2016

Environmental Impact Assessment started